Customer Case 1

 

 

225KWh stacked  lithium batteries in Belgium

 

 

 

Mr. Leenaerts needs 225KWh stacked lithium batteries in Belgium . It takes us 20 days production and about 60 shipping days. After installed, the project save about $11,250 annully for Leenaerts.

Stackable Battery

 

 

 

Customer Case 2

 

 

 

 

 

Mr. Christian needs 1500KW 3028KWh BESS in Philippines. It takes us 40 days production and about 15 shipping days. After installed, the project save about $151,400 annully for Christian.

1500KW 3028KWh  BESS in Philippines

1500KW 3028KWh  BESS

 

Customer Case 3

 

 

31-1

 

 

 

Mr. Jose needs 1160KWh lithium batery in Argentina. It takes us 20 days production and about 60 shipping days. After installed, the project save about $580,000 annully for Jose.

06

 

 

Customer Case 4

 

 

 

 

 

Mr. Boric needs 180KWh energy storage system in Croatia. It takes us 20 days production and about 50 shipping days. After installed, the project save about $9,000 annully for Boric.

37

08

 

Customer Case 5

 

 

4561453091221704576781559903740350046114421140n1

 

 

 

Mr. Manuel needs 500KW 2096KWh(2MWh) BESS in Netherlands.It takes us 40 days production and about 60 shipping days. After installed, the project save about $104,800 annully for Manuel.

10

 

Customer Case 6

 

 

 

 

 

Mr. 유승훈 needs 215KWh BESS in South Korea. It takes us 20 days production and about 20 shipping days. After installed, the project save about $10,750 annully for 유승훈.

1

12

 

 

Customer Case 7

 

 

11-3

 

 

 

Mr. Tomas needs 500KWh lithium batteries in Lithuania.It takes us 20 days production and about 60 shipping days. After installed, the project save about $25,000 annully for Tomas.

14

 

 

Customer Case 8

 

 

 

 

 

Mr. Jens-Ole needs 5MWh lithium batteries in Denmark.It takes us 40 days production and about 60 shipping days. After installed, the project save about $250,000 annully for Jens-Ole

17142752469231

16

 

 

Customer Case 9

 

 

2025021813354711

 

 

 

Mr. Ha needs 500KW 1164.8KWh (1MWh) BESS in Vietnam.It takes us 40 days production and about 15 shipping days. After installed, the project save about $58,240 annully for Mr. Ha.

18

 

Customer Case 10

 

 

 

 

 

Mr. Jimi needs 10MWh BESS in Hungary. It takes us 40 days production and about 60 shipping days. After installed, the project save about $500,000 annully for Mr. Jimi.